How Long Does It Take to Produce and Deliver Custom Dining Chairs from China?
- Sunbin Qi
- 2 days ago
- 4 min read
Updated: 2 days ago
When you're deep in the furniture industry, especially dealing with customized dining chairs, one question that often hangs in the air (and inbox) is: "How long will it actually take?" Trust me—I get it. After more than 20 years of guiding European furniture buyers through this maze, I've felt the anxiety and excitement myself.

So, let me walk you through this, step-by-step, sharing insights from my personal journey.
Initial Conversations and Specifications (1-2 weeks)
Every great piece of furniture starts with a detailed conversation. This stage might seem straightforward, but clarity here sets the foundation for everything else. When discussing your customized dining chair project, we go deep into specifics—fabric choices, frame materials, precise dimensions, and even the desired feel and comfort level of the chairs.
I remember vividly a project we did for a high-end restaurant chain in Hamburg. The buyer, Markus, had very particular requirements. He wanted something sleek yet extremely durable. After a week of emails, video calls, and sketches going back and forth, we nailed down exactly what he envisioned. This clarity upfront not only saved us time later but also ensured Markus got exactly what he expected.
Sample Production (10 days)
Next comes sample production. At ASKT, we've streamlined this process remarkably, primarily because of our dedicated craftsman Wei, who’s been cutting chair patterns expertly for over 20 years. A sample typically takes about 10 days to complete from the moment your design is finalized.
Creating samples quickly isn't about rushing—it’s about efficiency. Our R&D center, equipped with advanced tools and machinery, allows us to rapidly translate your vision into reality without sacrificing quality.

Batch Production (4-6 weeks)
After you've approved your custom sample, it's full steam ahead into batch production, which usually takes about 4-6 weeks. Here’s the inside story on why:
Material Preparation: Fabric sourcing alone can be a hidden pitfall. Many factories face delays simply because they underestimate fabric complexities. At ASKT, we pre-source and stock high-quality, certified fabrics to bypass potential delays. This proactive approach has saved countless weeks.
Manufacturing Process: Investing in cutting-edge equipment like automatic welding robots, fabric-cutting machines, and specialized assembly lines dramatically improves our production speed without sacrificing quality. Each welding joint is meticulously checked and verified, ensuring you don’t end up with chairs that wobble or squeak.
Rigorous Quality Control: This phase isn’t rushed. We’ve invested heavily in our quality inspection processes. Every chair undergoes numerous rigorous tests—from seat durability and backrest strength to fabric color fastness. We record video evidence of these tests for transparency and trust.

Shipping and Logistics (4-6 weeks by Sea, 5-10 days by Air)
Shipping times can vary greatly depending on your preferred method and destination. Typically, European destinations like Germany, Poland, and the Netherlands take around 4-6 weeks by sea. If you need your chairs faster, expedited air shipping can deliver in as little as 5-10 days, though at a higher cost.
Step | Typical Lead Time |
Initial Discussion & Specs | 1-2 weeks |
Customized Sample Production | ~10 days |
Batch Production | 4-6 weeks |
Sea Shipping (Europe) | 4-6 weeks |
Air Shipping (Expedited) | 5-10 days |
Total (Sea) | 9-14 weeks |
Total (Expedited Air) | 7-9 weeks |
I’ll never forget an urgent order we had from a customer in Dublin. They needed chairs rapidly for an unexpected restaurant opening. Using expedited air shipping, we delivered in record time. It felt like scoring a winning goal in the last minute—immensely satisfying.
Navigating Customs and Compliance (1 week)
Customs clearance is a step often overlooked. Thankfully, at ASKT, we've streamlined this too. By proactively implementing zero-plastic packaging practices, we've significantly reduced customs-related delays. Our honeycomb paper packaging isn’t just eco-friendly; it’s customs-friendly too, allowing your shipment to clear faster.

Realistic Expectations: Idea to Arrival (9-14 weeks)
From initial concept discussions to chairs snugly stacked in your warehouse, realistically plan for 9-14 weeks. While this might seem lengthy, clear expectations set the stage for smoother operations and fewer surprises.
Here’s my seasoned advice from two decades in the trenches:
Early Communication: Engage early and share every detail clearly. The more specific you are at the start, the faster and more accurate the production will be.
Clear Specifications: Clear documentation prevents costly misunderstandings and delays. A few extra hours upfront can save weeks later.
The Importance of a Buffer
Even with meticulous planning, unexpected events—like port congestion, extreme weather, or global disruptions—can throw timelines off track. Over the years, I've learned always to advise clients to add an extra buffer of 1-2 weeks. This extra time is like an insurance policy; hopefully unnecessary, but incredibly comforting when things go awry.
Final Thoughts: Partnership Over Production
At ASKT, lead time isn't just about counting days—it’s about building relationships. We emphasize transparency every step of the way because it builds trust. It's why we continue investing in advanced equipment, sustainable practices, and highly skilled talent. We’re not just making chairs—we’re creating partnerships.

Behind every chair is your vision, the comfort of your customers, and a little piece of my own passion. Keeping conversations open and expectations clear ensures we both celebrate that moment when your chairs arrive perfectly on schedule.
Warm regards,
Sunbin Qi
CEO, ASKT Furniture